Western shoreline construction

Construction will begin on Lakeside’s western shoreline the first week of December. Trucks will be entering Second Street and the Fifth Street Gates with areas roped off for safety.

KS Associates, located in Elyria, Ohio, continues to be the project lead. The plan is first to place toe stone (large in the water stone) embedded two feet into the lakebed. The large toe stone will help dissipate the waves and energy along this location.

New armor stone will be placed along the slope of the existing revetment on top of the toe stone. This will prevent long-term erosion along the western shoreline.