Order of Street Work Changes: Mill and fill work begins on Tuesday, Oct. 14. The contractor has reevaluated the project and determined a switch in the order of the street work. This change will provide a better finished project.
First, work will be performed on north/south streets. Second, work will be performed on east/west streets. Street work will be completed on every other street as previously planned. Owners in the first couple of streets will want to move cars on Tuesday, October 14, before 8 a.m. if traveling.
North/South Streets
- Poplar Avenue
- Cherry Avenue
- Peach Avenue – Ross Court
- Laurel Avenue
- Elm Avenue
- Plum Avenue
- Vine Avenue
- Oak Avenue
East/West Streets
- Second Street
- Fourth Street
- Sixth Street
- Third Street
- Fifth Street
Keeping you up to date on changes: We understand this is different than what was previously planned and communicated, but we want to provide the contractor with the best opportunity to complete the project with the best results.
Trash: Street Contractors will work with the trash trucks on Tuesday.