Mill and Fill work begins on October 9
First, contractors will begin with East and West streets. North and South streets will follow. This schedule is more efficient for the contractors.
Contractors will skip every other street, allowing cottage owners to access their property from the nearby street. According to the construction timeline, contractors will work about six total days on the mill work, followed by full-depth repairs for about six days, and then paving for about eight days, weather permitting.
Manholes and water valves will be adjusted to the new pavement, and then new stop signs and striping will be added. The street order will be as follows:
East/West Streets
- Second St.
- Fourth St.
- Sixth St.
- Third St.
- Fifth St.
North/South Streets
- Poplar Ave.
- Cherry Ave.
- Peach Ave. & Ross Court
- Laurel Ave.
- Elm Ave.
- Plum Ave.
- Vine Ave.
- Oak Ave.
Updates & Safety: We will provide daily updates as work begins on October 9. Please be careful around all construction equipment during the project.
Lakeside-Marblehead Lighthouse Festival: For the Lakeside-Marblehead Lighthouse Festival on Saturday, Oct. 11, gates will be open; however, the Second Street entrances and Fourth Street entrance may have significant delays.
Trash & Leaves: In the first week, trash will be picked up before work begins on October 9. We will work during the second week to ensure all trash is picked up and emptied. View Leaf Pick Up Schedule, starting Oct. 27.
Parking & Traffic: Residents in the 100 Block of Oak Ave. can park in the marina parking lot outside of the gate. Please note that the gate is closed from 9 p.m.-6 a.m. Also, individuals will need to move vehicles by 8 a.m. in areas where construction occurs.